WHEN WILL CONSTRUCTION START?

Construction will begin in August 2019.

The Department of Education has a Funding Cycle and must approve building plans for new facilities. The first Funding Cycle after our millage passed was May of 2019. 

This allowed us a year to work with our construction team to draw up plans and itemize all related costs to meet timelines and maximize our available resources. 

 

 

ARE WE STILL ON SCHEDULE?

Yes! We have told patrons that all building projects would be completed and ready to occupy by the beginning of the 2021-2022 School Year, and we are on track to do so.

 

. . . . . . .

 

Performing Arts Center 

Construction will begin in September of 2019.

Front view performing arts center.

Side view performing arts center.

 

 

Junior High School (Grades 7-8)

Construction will begin in November 2019. 

Junior High side view

JH front view

 

LPS & LIS Cafeterias 

Construction will begin in January of 2020.

The cafeterias are being built in the time frame presented to allow our students to have usable cafeteria spaces the maximum amount of time during construction.

Primary entrance & cafeteria

Intermediate entrance & cafeteria


 

Turf Practice Field 

The project will be completed by January 2020, allowing our students to have two fields for the maximum amount of time during construction. 

Practice Turf Field